In a decision dated October 30, 2018, Supreme Court Judge Joseph Pastoressa remanded a decision made by the Southampton Village Architectural and Historic Board (BARHP) for further consideration. Manger et al. v. Board of Architectural Review and Historic Review of the Village of Southampton.

 The property owner in Manger applied to the BARHP

Local zoning ordinances throughout New York State incorporate the flexible “accessory use” component so as not to unnecessarily restrict one’s use of property.  Accessory uses are incidental and customary to the principal use of property. Determining whether a use is actually “accessory,” however, is often debated – especially where the use is not specifically enumerated

On September 26, 2018, the Federal Communications Commission (FCC) adopted its Declaratory Ruling and Third Report and Order (“Declaratory Ruling and Order”) enacting significant regulatory changes that will impact local control over the deployment of wireless infrastructure. Aimed at streamlining the nationwide deployment of 5G wireless—the next generation of wireless technology—the Declaratory Ruling and Order

In Voutsinas v. Schenone, 2018 NY Slip Op 07439 (2d Dept, November 17, 2018), the Appellate Division, Second Department, reminded land use practitioners of not only the importance of appealing decisions rendered by Town and Village Boards, including Trustees, Zoning and Planning Boards, even if not all of the findings of facts in the

The Appellate Division, Second Department, issued a decision on October 10, 2018, which rejected a town’s attempt to saddle an applicant with over $17,000 in consulting fees supposedly incurred by the town in reviewing special use permit and area variance applications for an antenna tower to be used by an amateur radio (a/k/a ham radio)

New York State Town Law § 277(9) authorizes a town Planning Board to require a developer to provide a performance bond or other security covering the cost of installation of subdivision infrastructure and improvements in case the developer fails to finish the required work. Specifically, Town Law §277(9) states: “[a]s an alternative to the installation

On October 17, 2018, the Supreme Court, Appellate Division, Second Department (“Second Department”) issued two (2) companion decisions arising out of three different attempts by Petitioners, Kleinknechts (“Petitioners”)  to construct a dock at their waterfront property.  Each of the attempts resulted in a Supreme Court litigation.  As we blog about these cases today, no dock

A use variance is arguably one of the most difficult zoning approvals to obtain and is rarely granted.  Petitioners in 54 Marion Ave., LLC v. City of Saratoga Springs, 2018 N.Y. Slip Op. 04611, 162 A.D.3d 1341 (3d Dep’t 2018),  commenced a hybrid proceeding/action to challenge and annul a determination of the Zoning

In Real Estate Bd. of New York, Inc. v. City of New York, Petitioner-Plaintiff Real Estate Board of New York, Inc. (“REBNY”) commenced a hybrid article 78 proceeding and plenary action against the City of New York (“City”) challenging the City’s adoption of Local Law No. 50 of 2015 (“

A recent decision from the Nassau County Supreme Court, Healy v. Town of Hempstead Board of Appeals, overturned a municipal determination that granted special zoning exceptions and variances to a Greek Orthodox Church located in Merrick, New York. The church wanted to construct a two-story cultural center and related parking next to the church.